AI verification workspace

Document and BOQ queue on the left, evidence viewer in the centre, AI findings and engineer decision on the right.

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Review queue

Evidence viewer — HLM-0718-0093

Site photograph
Site photograph evidencing Internal cement plaster — Floors 5-7 at AR-DWG-204 Rev C
Internal cement plaster — Floors 5-7HLM-0718-0093 · AR-DWG-204 Rev C · RFA-0431 (pending)
RFA-to-BOQ and SMM7 matching Passed
Drawing / specification compliance Passed
Duplicate or reused evidence Passed
Work claimed before approval Passed
Quantity and measurement mismatch Passed
Unsupported variation Passed
Claimed progress exceeding photographed progress Passed
Previous-period double counting Passed
Cost-to-complete risk Passed

AI findings & engineer decision

High · 94%Evidence complete

Claimed 13,300 m2 for the period. Helmet imagery dated 18-Jul-2026 confirms plaster complete on Floors 5 and 6 only (8,348 m2). Floor 7 shows blockwork stage. RFA-0431 covering Floor 7 remains unapproved by the consultant.

Calculation steps

  1. Claimed value: AED 612,000
  2. Evidence-supported quantity applied at BOQ rate AED 46/m2
  3. Supported value: AED 384,000
  4. Variance withheld: AED 228,000

Source citations

  • BOQ 4.02.01 · Internal cement plaster, two coats, to walls
  • RFA-0431 (pending)
  • AR-DWG-204 Rev C
  • IPC-016 §4.02.01
  • HLM-0718-0093
AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.