Bank Risk Center

Portfolio-level escrow assurance: what has been lent, what has genuinely been built, and where the exposure sits.

Portfolio exposure

AED 1.20B

9 escrow-linked facilities

Loan disbursed

AED 691.50M

57.5% of facility drawn

Verified asset progress

47.2%

Weighted by exposure — 3.1pp below claimed

Projects on hard stop

3

AED 286.40M exposed

Disbursement funnel

Schedule & budget trend — Al Noor Residences

Draw requests awaiting decision

IPCProjectClaimedSupportedStage
IPC-017Al Noor ResidencesAED 8.45MAED 7.82Mengineer review
IPC-031Marsa Bay TowersAED 14.20MAED 14.02Mrecommended
IPC-012Khalifa Logistics Park Ph2AED 9.64MAED 8.91Minspection
IPC-008Ajman Corniche OfficesAED 4.32MAED 4.18Mai review
IPC-005Reem Island Medical CampusAED 12.90MAED 12.76Mbank review
IPC-041Al Zorah Lagoon ApartmentsAED 1.96MAED 1.96Mrecommended

Transparent risk score — Al Noor Residences

Composite score 78/100. Every contributing factor is shown with its weight; nothing is hidden in a black box.

  • Claimed vs verified progress gap22 / 25

    3.4 percentage points, 3 consecutive periods

  • Exception density per IPC17 / 20

    6 exceptions, 2 critical

  • Schedule variance16 / 20

    11% behind baseline programme

  • Cost-to-complete headroom11 / 15

    Forecast AED 2.1M above remaining facility

  • Contractor concentration7 / 10

    Gulf Horizon holds 2 projects, AED 180.4M exposure

  • Evidence quality5 / 10

    1 duplicate photograph, 1 missing RFA approval

Cost to complete — Al Noor Residences

Cost incurred (certified)
AED 78,900,000
Committed cost (orders placed)
AED 41,200,000
Remaining contingency
AED 3,400,000
Forecast cost to complete
AED 109,800,000
Remaining facility
AED 53,500,000
Forecast shortfall
− AED 2,100,000

Counterparty concentration & related-party flags

ContractorProjectsExposureExceptionsScoreRelated-party flag
Gulf Horizon Contracting LLC2AED 180.40M874Shares director with Al Noor Properties LLC
Falcon Ridge Builders2AED 154.00M2088
Delta Peninsula Construction2AED 528.00M226
Northern Bay Contracting2AED 150.00M022
Zayed Steel & Civil LLC1AED 190.00M448
AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Drill-down path: portfolio → project IPC evidence.