IPC-005 — July 2026

Reem Island Medical Campus, Abu Dhabi · Delta Peninsula Construction · Reviewer Eng. Layla Haddad

bank review
  1. 1. Contractor IPA

  2. 2. Consultant verification

  3. 3. Developer acknowledgement

  4. 4. Bank draw request

  5. 5. Document review

  6. 6. AI pre-inspection plan

  7. 7. Physical inspection

  8. 8. Engineer review

  9. 9. IPC recommendation

  10. 10. Bank release / hold

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Valuation summary

Gross claimed
AED 12,900,000
AI-supported
AED 12,760,000
Engineer adjusted
AED 12,760,000
Previous certified
AED 31,900,000
Current certified
AED 12,760,000
Retention withheld
− AED 1,276,000
Advance recovery
− AED 1,290,000
Variations
+ AED 0
Net recommended disbursement
AED 10,194,000

Claimed progress 14.6%

AI-verified progress 14.1%

Unsupported variance

AED 140K

1.1% of the claim

Open exceptions

1

1 critical

Progress gap

0.5 pp

Claimed minus independently verified

Exception register

Select any row to inspect the linked evidence chain.

SeverityBOQ itemClaimVerifiedVarianceIssueConfidenceEvidenceReviewer
critical4.02.01

Internal cement plaster — Floors 5-7

AED 612,000AED 384,000− AED 228,000Premature claim

Claimed progress exceeds photographed progress; Floor 7 plaster not started at inspection date

High · 94%completeEng. Rashid Al Mansoori

Decision actions

Segregation of duties: inspectors recommend, banks release. Your role — Bank Risk Manager may release or hold escrow funds but cannot amend inspection evidence.

View the full audit trail for Reem Island Medical Campus