IPC-005 — July 2026
Reem Island Medical Campus, Abu Dhabi · Delta Peninsula Construction · Reviewer Eng. Layla Haddad
1. Contractor IPA
2. Consultant verification
3. Developer acknowledgement
4. Bank draw request
5. Document review
6. AI pre-inspection plan
7. Physical inspection
8. Engineer review
9. IPC recommendation
10. Bank release / hold
Valuation summary
- Gross claimed
- AED 12,900,000
- AI-supported
- AED 12,760,000
- Engineer adjusted
- AED 12,760,000
- Previous certified
- AED 31,900,000
- Current certified
- AED 12,760,000
- Retention withheld
- − AED 1,276,000
- Advance recovery
- − AED 1,290,000
- Variations
- + AED 0
- Net recommended disbursement
- AED 10,194,000
Claimed progress 14.6%
AI-verified progress 14.1%
Unsupported variance
AED 140K
1.1% of the claim
Open exceptions
1
1 critical
Progress gap
0.5 pp
Claimed minus independently verified
Exception register
Select any row to inspect the linked evidence chain.
| Severity | BOQ item | Claim | Verified | Variance | Issue | Confidence | Evidence | Reviewer |
|---|---|---|---|---|---|---|---|---|
| critical | 4.02.01 Internal cement plaster — Floors 5-7 | AED 612,000 | AED 384,000 | − AED 228,000 | Premature claim Claimed progress exceeds photographed progress; Floor 7 plaster not started at inspection date | High · 94% | complete | Eng. Rashid Al Mansoori |
Decision actions
Segregation of duties: inspectors recommend, banks release. Your role — Bank Risk Manager — may release or hold escrow funds but cannot amend inspection evidence.