IPC-017 — July 2026

Al Noor Residences, Ajman · Gulf Horizon Contracting LLC · Reviewer Eng. Rashid Al Mansoori

engineer review
  1. 1. Contractor IPA

  2. 2. Consultant verification

  3. 3. Developer acknowledgement

  4. 4. Bank draw request

  5. 5. Document review

  6. 6. AI pre-inspection plan

  7. 7. Physical inspection

  8. 8. Engineer review

  9. 9. IPC recommendation

  10. 10. Bank release / hold

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Valuation summary

Gross claimed
AED 8,450,000
AI-supported
AED 7,820,000
Engineer adjusted
AED 7,905,000
Previous certified
AED 71,120,000
Current certified
AED 7,905,000
Retention withheld
− AED 790,500
Advance recovery
− AED 422,500
Variations
+ AED 315,000
Net recommended disbursement
AED 7,007,000

Claimed progress 46.8%

AI-verified progress 43.4%

Unsupported variance

AED 630K

7.5% of the claim

Open exceptions

6

2 critical

Progress gap

3.4 pp

Claimed minus independently verified

Exception register

Select any row to inspect the linked evidence chain.

SeverityBOQ itemClaimVerifiedVarianceIssueConfidenceEvidenceReviewer
critical4.02.01

Internal cement plaster — Floors 5-7

AED 612,000AED 384,000− AED 228,000Premature claim

Claimed progress exceeds photographed progress; Floor 7 plaster not started at inspection date

High · 94%completeEng. Rashid Al Mansoori
critical8.02.01

Unitised facade — Zone A panels

AED 894,000AED 712,000− AED 182,000Quantity mismatch

Quantity mismatch between claimed panel count and delivered/installed count

High · 89%partialEng. Rashid Al Mansoori
major5.01.02

Wet area waterproofing — Podium

AED 268,000AED 268,000Duplicate evidence

Evidence photograph reused from IPC-015 (perceptual hash match 0.97)

High · 97%missingEng. Layla Haddad
major7.04.02

Marble cladding — Lift lobby L1-L3

AED 148,000AED 96,000− AED 52,000Unsupported variation

Unsupported variation: imported marble grade upgraded without approved VO

Medium · 81%partialEng. Omar Farouk
minor6.03.05

Concealed conduits — Floors 3-4

AED 214,000AED 196,000− AED 18,000Double counting

Previous-period double counting on 640 m of ceiling conduit

High · 86%completeEng. Rashid Al Mansoori
minor10.02.03

Robotic-sprayed screed — new method

AED 78,000AED 78,000Needs engineer input

No SMM7 code mapping available — routed for engineer input

Low · 41%completeUnassigned

Decision actions

Segregation of duties: inspectors recommend, banks release. Your role — Bank Risk Manager may release or hold escrow funds but cannot amend inspection evidence.

View the full audit trail for Al Noor Residences