IPC-024 — July 2026

Al Hamra Coastal Villas, Ras Al Khaimah · Northern Bay Contracting · Reviewer Eng. Layla Haddad

released
  1. 1. Contractor IPA

  2. 2. Consultant verification

  3. 3. Developer acknowledgement

  4. 4. Bank draw request

  5. 5. Document review

  6. 6. AI pre-inspection plan

  7. 7. Physical inspection

  8. 8. Engineer review

  9. 9. IPC recommendation

  10. 10. Bank release / hold

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Valuation summary

Gross claimed
AED 3,180,000
AI-supported
AED 3,140,000
Engineer adjusted
AED 3,140,000
Previous certified
AED 48,560,000
Current certified
AED 3,140,000
Retention withheld
− AED 157,000
Advance recovery
− AED 159,000
Variations
+ AED 0
Net recommended disbursement
AED 2,824,000

Claimed progress 71.4%

AI-verified progress 69.8%

Unsupported variance

AED 40K

1.3% of the claim

Open exceptions

0

0 critical

Progress gap

1.6 pp

Claimed minus independently verified

Exception register

Select any row to inspect the linked evidence chain.

SeverityBOQ itemClaimVerifiedVarianceIssueConfidenceEvidenceReviewer

Decision actions

Segregation of duties: inspectors recommend, banks release. Your role — Bank Risk Manager may release or hold escrow funds but cannot amend inspection evidence.