IPC-031 — July 2026

Marsa Bay Towers, Dubai · Delta Peninsula Construction · Reviewer Eng. Layla Haddad

recommended
  1. 1. Contractor IPA

  2. 2. Consultant verification

  3. 3. Developer acknowledgement

  4. 4. Bank draw request

  5. 5. Document review

  6. 6. AI pre-inspection plan

  7. 7. Physical inspection

  8. 8. Engineer review

  9. 9. IPC recommendation

  10. 10. Bank release / hold

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Valuation summary

Gross claimed
AED 14,200,000
AI-supported
AED 14,020,000
Engineer adjusted
AED 14,020,000
Previous certified
AED 187,280,000
Current certified
AED 14,020,000
Retention withheld
− AED 701,000
Advance recovery
− AED 710,000
Variations
+ AED 120,000
Net recommended disbursement
AED 12,729,000

Claimed progress 61.2%

AI-verified progress 60.1%

Unsupported variance

AED 180K

1.3% of the claim

Open exceptions

1

1 critical

Progress gap

1.1 pp

Claimed minus independently verified

Exception register

Select any row to inspect the linked evidence chain.

SeverityBOQ itemClaimVerifiedVarianceIssueConfidenceEvidenceReviewer
critical4.02.01

Internal cement plaster — Floors 5-7

AED 612,000AED 384,000− AED 228,000Premature claim

Claimed progress exceeds photographed progress; Floor 7 plaster not started at inspection date

High · 94%completeEng. Rashid Al Mansoori

Decision actions

Segregation of duties: inspectors recommend, banks release. Your role — Bank Risk Manager may release or hold escrow funds but cannot amend inspection evidence.

View the full audit trail for Marsa Bay Towers