Khalifa Logistics Park Ph2 — Abu Dhabi
Nawah Industrial Developments · Zayed Steel & Civil LLC · Kestrel Partners · Capital Trust Bank (demo data)
Contract value
AED 268.75M
Design and build · NEC4 Option C
Bank exposure
AED 190.00M
AED 96.40M disbursed
Claimed vs verified
38.5% / 35.9%
Engineer certified 36.4%
Schedule variance
-7%
Completion 2027-06-01
Claimed vs verified vs planned progress
AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.
Contract particulars
- Contract type
- Design and build
- Form of contract
- NEC4 Option C
- Commencement
- 2024-11-04
- Contractual completion
- 2027-06-01
- Retention
- 10%
- Defect Liability Period
- 24 months
- Units
- n/a
- Advance recovery
- 10%, pro-rata from IPC-004
- Variations approved
- 3 (AED 1.42M)