Emirates Gate Mall Extension — Dubai

Gateway Retail Investments · Falcon Ridge Builders · Arcadia Consult · Gulf Union Bank (demo data)

Risk score 81hard stopOpen IPC-019

Contract value

AED 158.90M

Lump sum · Authority-specific conditions (DLD)

Bank exposure

AED 112.00M

AED 88.10M disbursed

Claimed vs verified

57.9% / 51.2%

Engineer certified 52.0%

Schedule variance

-14%

Completion 2026-11-20

Claimed vs verified vs planned progress

AI-assisted — Professional Engineer approval required. Figures are model-generated from submitted evidence and are not certified until an engineer signs off.

Contract particulars

Contract type
Lump sum
Form of contract
Authority-specific conditions (DLD)
Commencement
2024-01-15
Contractual completion
2026-11-20
Retention
10%
Defect Liability Period
12 months
Units
n/a
Advance recovery
10%, pro-rata from IPC-004
Variations approved
3 (AED 1.42M)